Begin: Tuesday, March 8th, 2022 at 4:00 am
End: Tuesday, March 8th, 2022 at 6:00 am
Building(s) or Area(s) Impacted: University Street and Esslinger Hall
Scope: Crane pick for new HVAC equipment and removal of old HVAC equipment on the roof of Esslinger.
Services Impacted:
- Traffic restrictions, rerouting and street side parking
- Sidewalk and street adjacent to project site will be marked off
Work Performed By: Harvey and Price
Contact: Kevin Waldrop, CPFM D&C Facilities Engineer, 541-346-2315