Begin: Tuesday, August 24th, 2021 at 7:00 am
End: Wednesday, August 25th, 2021, 2021 at 6:00 pm
Building(s) or Area(s) Impacted: Onyx Bridge
Scope: Each HVAC unit will be shut down for approximately ½ – 1 day during the timeframe indicated to perform cleaning. This is part of the wildfire insurance response project.
Services Impacted: HVAC units will be offline.
- 8-24-2021 – First floor through – Fourth Floor & EHS 90 Day Area
- 8-25-2021 – EHS Office Areas
Note: Fume hood sashes will need to be closed and containers within the fume hoods sealed prior to the shutdown.
Work Performed By: ERS, Inc.
Contact: Adam Jones, SRS Buildings Sciences Manager, 541-346-8397