UPDATE 12/05/25:
- Wednesday, December 10, 2025 – Saw cutting of epoxy top, noise can be expected starting at 8:00 am and ending no later than 1:00 pm
- Thursday, December 11, 2025 – Core drilling of concrete, starting at 6:00 am and ending no later than 1:00 pm
Begin: Tuesday, December 2, 2025, at 7:00 am
End: Friday, January 2, 2026, at 4:00 pm
Building(s) or Area(s) Affected: Streisinger Hall room 276
Scope: The lab’s casework will be reconfigured in room 276. This includes moving a sink and modifying existing casework. Demo, new finishes, plumbing and electrical will also be involved. The plumbing scope will require core drilling and a one-day plumbing shutdown that effects Streisinger Hall rooms 276, 275, 255, and 265. A separate notification will go out for the core drilling and plumbing shutdown once those are scheduled.
Services Impacted:
- Users can expect to see contractors working in room 276 and mechanical room 190.
- There will be periodic noise and vibrations as work continues.
- The core drilling and plumbing shutdown will be scheduled and a separate shutdown update will be sent out for this work.
Work Performed By: Store & Stock LLC and Brothers Plumbing
Contact: Glen Macdonald, CPFM Owner’s Representative, 541-346-8201