UPDATE:
As part of the abatement work associated with this project, the HVAC will need to be shut down to rooms 112, 116, and 250 – 259.
Begin: Monday, August 26, 2024, at 7:00 am
End: Friday, August 30, 2024, at 4:00 pm
Building(s) or Area(s) Affected: Esslinger Hall
Scope: Contractor will perform abatement services to remove asbestos containing material from rooms 112 and 116.
Services Impacted:
- Containment will be enclosed to those two rooms only, but containment access will take up to 4′ into the hall wall.
- Passage is still provided.
- Noise associated with this activity can be expected during this time.
Work Performed By: Asbestos Abatement Contracting, LLC.
Contact: Waymon Banks, CPFM Owner’s Representative, 541-346-0196