10/07/25 – 1/09/26 Klamath Hall Steam Coil Replacement Advisory

UPDATE 12/05/25:  All steam shutdowns are being pushed back until Spring, an updated notice will be sent out when more information is available.

Begin:  Tuesday, October 7, 2025, at 7:00 am

End:      Friday, January 9, 2026, at 4:00 pm

Building(s) or Area(s) Affected:  Klamath Hall

Scope:  The steam coils will be replaced in the Klamath Hall basement.

Services Impacted:

  • For most of the duration of the project, there won’t be much disruption.
  • There will be welding and soldering occurring in the basement, but the contractor will be taking steps to minimize odors throughout the building.
  • As part of this project, the steam and air handlers will have to be shutdown periodically.  Additional, updated notifications and coordination will take place prior to these shutdowns. I don’t have a schedule of those yet.

Work Performed By:  Brothers Plumbing

ContactGlen Macdonald, CPFM Owner’s Representative, 541-346-8201

Current construction and impacts information can be found on the UO Maps site.