UPDATE:
This work has been postponed and will now be completed on 6/10/25.
Begin: Thursday, June 5 Tuesday, June 10, 2025, at 8:00 am
End: Thursday, June 5 Tuesday, June 10, 2025, at 12:00 noon
Building(s) or Area(s) Affected: McKenzie Hall and Computing Center
Scope: The chilled water that feeds McKenzie Hall will be shut down to install a new valve coming from Villard Hall.
Services Impacted:
- Chilled water to McKenzie Hall and Computing Center will be temporarily shut off to install a new valve.
- Chilled water will be down for 2-4 hours affecting the building’s cooling system.
- Arrangements are being made with Computing Center to initiate backup chilled water for the down time, along mitigating air intrusion.
Work Performed By: Fortis/Alliant
Contact: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214
Current construction and impacts information can be found on the UO Maps site.