Begin:  Monday, January 22, 2024, at 8:00 am

End:      Monday, January 22, 2024, at 10:00 am

Building(s) or Area(s) Affected:  Huestis Hall, Lokey Labs, Streisinger Hall, Willamette Hall

Scope:  A contractor will be performing a short verification test of the newly installed compressed air valves and BAS alarms, as part of commissioning and final UO acceptance.

Services Impacted:  It is expected to have no effect on your normal operations.

Work Performed By:  Siemens, JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880