1/25/24 and 2/08/24 Huestis Hall Basement Domestic and Industrial Water Shutdown

UPDATE 2/06/24:
The valves for this shutdown have arrived, however the contractor has additional prep work to perform prior to the shutdown that was unforeseen.  This shutdown will occur on Thursday, February 8th from 7:00 am – 1:30 pm.

 

UPDATE 1/31/24:
The domestic water valves have arrived.  Work will take place on Wednesday, February 7th, from 7:00 am to 1:30 pm.
– Domestic hot and cold water will be offline.
– Restroom and handwashing sink fixtures will not be available during this outage.

 

UPDATE 1/23/24:
Delivery of the domestic water valves is delayed. Tomorrow’s shutdown for January 24th will be rescheduled for a later date.  A new shutdown notice will be distributed.

The project is proceeding with the Thursday, January 25th  industrial water shutdown from 7:00 am – 1:30 pm.   However, the shutdown affects industrial hot water only. There are no anticipated impacts to RO generation and therefore, the bypass is not necessary.

 

BeginJanuary 24, Thursday, January 25, 2024, at 7:00 am

End:      Thursday, January 25, 2024, at 1:30 pm

Additional Date:  Thursday, February 7 8, 2024, from 7:00 am to 1:30 pm

Building(s) or Area(s) Affected:  Huestis Hall basement

Scope:  Contractor will install control valves on the existing domestic and industrial water lines over two days.

Services Impacted:

  • January 24, February 7, Thursday, February 8, 7:00 am – 1:30 pm:  Domestic hot and cold water will be offline. Restroom and handwashing sink fixtures will not be available during this outage.
  • Thursday, January 25, 7:00 am – 1:30 pm:  Industrial and RO water service will be offline. Bypass valve will be open to provide cold water for the RO generator.

Work Performed By:  Siemens and JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.