7/24/23 Huestis Hall Basement AHU1 and 2 Shutdown

Begin:  Monday, July 24, 2023, at 7:00 am

End:      Monday, July 24, 2023, at 12:00 noon

Building(s) or Area(s) Affected:  Huestis Hall Basement

Scope:  Shutdown of AHU 1 and 2 serving the basement will be offline to clean the VFDs as part of the constructions and preventative maintenance plan.

Services Impacted:  Supply and exhaust air will be offline during this time.

Work Performed By:  EC and Siemens

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall