Begin: Tuesday, June 20, 2023
End: Friday, June 23, 2023
Building(s) or Area(s) Affected: Oregon Hall – H280, H285, 285, 284, 283, 282,279, 278, 280, and 281 H385, H386, 382,387, 386, 385, 384, 383, and 376
Scope: We will be conducting a GPR (ground penetrating radar) investigation of the 3rd floor slab in specific areas of the SE portion of Oregon Hall on Tuesday, June 20th – Friday, June 23rd. See attached plan for the general areas we are targeting. Most of this investigation will be conducted in the currently unoccupied space on the 3rd floor. We will be accessing the ceiling of the second floor offices for one day of the investigation. I will be coordinating with those offices to mitigate the disruption while we capture this data.
Services Impacted:
- This will mostly impact those on the rooms listed in the second floor for one day as the crew comes through their offices to scan their ceilings.
- Noise can be expected during this time.
Work Performed By: Concrete GPR
Contact: Janell Cottam, CPFM Owner’s Representative, 541-346-7536
Current construction and impacts information can be found on the UO Maps site.
2ndFlr_StructureOverlay3rdFlr_StructureOverlay3rdFlr_StructureOverlay