Lawrence Hall Access Advisory 3/21/22

Begin:  March 21, 2022 at 8:00 AM

End:      March 21, 2022 at 4:00 PM

Building(s) or Area(s) Impacted:  Lawrence Hall

Scope:  In preparation for replacement of the glass curtain wall at the Lawrence Hall Stair tower on the SW side of the building, a boom lift will be in use for the day to take measurements on the window opening.

Services Impacted:  The stairwell and the exit from the exterior door nearest the stairwell will remain open, but the lift may limit access directly around the base of the stairwell.

Work Performed By: Andersen Construction

Contact: Luke Helm, CPFM Owner’s Representative, 541-346-8216