Begin: Wednesday, January 12th, 2022 at 8:00 am
End: Wednesday, January 12th, 2022 at 12:00 noon
Building(s) or Area(s) Impacted: CPFM Warehouse/Shops (Bldg. 130)
Scope: Due to the delivery of a container spray booth, the north side of the CPFM Warehouse will be closed to parking and through traffic. This will allow a crane to offload and place the booth near the FS Paint Quonset.
Services Impacted: The parking lot and travel lanes north of the CPFM Warehouse Bldg. 130 will not be accessible, requiring traffic to detour.
Special Instructions: Traffic for Stores will be rerouted through the east gate, past ZIRC, and out to Riverfront Parkway via the gravel road south of the greenhouses.
Work Performed By: Facilities Services and subcontractors
Contact: Justin Grishkin, CPFM Construction Services Manager, 541-346-5242