UPDATE 8/18/21: The contractor is ahead of schedule and will be completing this work on August 19, 2021.
Begin: Friday, August 20 19th, 2021 at 7:00 am
End: Friday, August 20 19th, 2021 at 6:00 pm
Building(s) or Area(s) Impacted: Allen Hall
Scope: Each HVAC unit will be shut down for approximately ½ – 1 day during the timeframe indicated to perform cleaning. This is part of the wildfire insurance response project. Note: this work excludes the computing center.
Services Impacted: HVAC units will be offline for the entire building except the data center.
Work Performed By: ERS, Inc.
Contact: Adam Jones, SRS Buildings Sciences Manager, 541-346-8397