Begin: March 18, 2021 at 9:00 am
End: March 18, 2021 at 12:00pm
Building(s) or Area(s) Impacted: North of Chilled Water Plant
Scope: Due to the replacement of cooling tower inlet louvers, a crane will be staged north of the CPFM Chiller Plant to lift equipment to the roof.
Services Impacted: Access will be limited. Proceed with caution.
Work Performed By: NW Mechanical
Contact: Kyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246