Pacific Hall HVAC Shutdown 2/1/21 – 3/9/21

UPDATE 3/8/21: Work is complete on the coil replacement, and the system will be brought back online tomorrow 3/9. Please be advised during startup there may be odors throughout the building, as steam will be introduced into the new steam coils.  Every effort will be made to mitigate any odor prior to startup of the Air Handler.

UPDATE 3/2/21: The repairs are still ongoing and work is expected to be complete by 3/9.

UPDATE 2/22/21: This work has been extended to 3/2 due to a parts delay.

Begin:  Monday, February 1st, 2021

End:      Monday, February 22nd, 2021 March 2, 2021 March 9, 2021

Building(s) or Area(s) Impacted:  Pacific Hall

Scope:  Due to work associated with the replacement of a failed steam coil, Air Handler 1 needs to be shut down while work is performed inside the air handler. This unit serves the north portion of the building only, which is heated by individual radiators.

Services Impacted:  Steam and other building services will not be affected.

Work Performed By:  S2 and Siemens

Contact: Jeff Madsen, CPFM Asst. Dir Engineer Utility Systems, 541-346-2256