Building or Area Impacted: Klamath Hall – Basement, 1st floor, and 2nd floor
Scope: Scope: Facilities Services is currently responding to the impacts of the recent fire/smoke event. As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.
Begin: Today, Tuesday, September 29th, 2020 at 12:30 pm
End: Today, Tuesday, September 29th, 2020 at 2:30 pm
Services Impacted: Fume hoods and building air will be offline. This will affect ½ of the building the first hour, and the 2nd half of the building the second hour, but it is unknown at this time which will be first.
Extra Notes: Attached is the link to the original campus wide emergency HVAC filter replacement project notice https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/
Special Instructions: Please close all fume hood sashes
Work Performed By: UO CPFM Facilities Services
Contact: Ken Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406