Recycling Quonset #134 and Paint Quonset #129 Seal Coating Advisory 9/28/20 – 10/30/20

UPDATE 10/26: The seal coating should be completed by the end of the week.

Begin:  Monday, September 28th, 2020

End:      Friday, October 23rd 30th, 2020

Buildings or Areas Impacted:  Recycling Quonset (Bldg. #134) and Paint Quonset (Bldg. #129)

Scope:  Preferred Construction is tentatively scheduled to start seal coating of the Recycling & Paint Quonsets next Monday. They will begin with cleanup and pressure washing and then apply the seal coat. A large articulating boom lift will be working around both Quonsets.

Services Impacted:  There will be a chemical odor associated with application.

Extra Notes:  We will be moving the Recycling vehicles and large metal containers, as needed, throughout the process.

Work Performed By:   Preferred Construction

ContactJeff Hanson, CPFM Construction Project Manager, 541-951-7195