Begin: Tuesday, May 17th, 2022 at 7:00 am
END: Tuesday, May 17th, 2022 at 12:00 noon
Building(s) or Area(s) Impacted: Lot 7B and entry on the west side of McKenzie Hall accessed through lot.
Scope: We are beginning a project to improve the ADA ramp and run power to charge electric vehicles, a sub-contractor will be saw cutting the asphalt and removing planting from the landscaping strip at lot 7B on the west side of McKenzie Hall.
Services Impacted: Access to the Parking lot, sidewalk and the ADA ramp will be impacted. Classrooms 229 and 240 will be most directly affected.
Extra Notes: they have the goal completing this before the first morning class for the nearest classrooms at 10:00 am.
Work Performed By: Andersen Construction, Cutting Edge Concrete
Contact: Luke Helm, CPFM Owner’s Representative, 541-346-8216