Facilities Liaisons,
As part of renovations, contractors need to access the north exhaust plenum on the roof to investigate upcoming work related to the third-floor project. To enter the plenum, the northern exhaust fans have to be off for safety.
General lab exhaust and fume hood exhaust will be offline to the north half of the building for all floors on Wednesday, May 29, for the two-hour duration (5 am – 7 am) at most. Work will be performed by Lease Crutcher Lewis.
Special Instructions:
The evening prior to the shutdown, Tuesday, May 28, fume hood sashes need to be closed in the north half of the building for all floors.
For questions or concerns, please contact CPFM Design and Construction Owners Rep Denise Stewart at 541-335-1258