Campus Community,
I just learned that the scope of the work at the intersection has changed and the intersection will not be closed on Friday the 17th. The full intersection will be re-opened on Monday with some temporary paving (crushed gravel) in a portion of the travel lanes. The permanent fix will occur later this summer.
Thank you for your patience.
Michael A. Harwood, FAIA
Associate Vice President and University Architect
Campus Planning and Facilities Management
University of Oregon
maharwoo@uoregon.edu
(541) 346-8267
______________________________________________________________________________________________________________________________
Facilities Liaisons,
As part of the Hayward Field Renovation, the contractor, Hoffman Construction has encountered a field condition related to grades that will require them to pour more concrete than they expected. This will necessitate closing the Onyx Street & East 15th Ave intersection starting at 6:00 am on May 17, removing the concrete in the morning and pouring the concrete in the afternoon. They would re-open the intersection at 6:00 am on Monday, May 20. Access to the parking lot will not be affected.
For questions or concerns, please contact the CPFM Project Manager:
Michael A. Harwood, FAIA
Associate Vice President and University Architect
Campus Planning and Facilities Management
University of Oregon
maharwoo@uoregon.edu
(541) 346-8267