Update –
After confirming with Utilities and Energy it has been determined that this chilled water shutdown will impact Straub. No other buildings should be impacted. This is a revision from the notice below. This will impact all equipment utilizing the chilled water loop in Straub.
________________________________________________________________________________________________________
Building Occupants,
Starting December 28, 2017 at 7:30 am ending December 29, 2017 at 9:00 am the chilled water will be shut down in the tunnel while new values are installed. This will impact chilled water to Living and Learning Center, University Health Counseling and Testing Center and possibly and Earl. This will impact all equipment utilizing the chilled water loop.
For questions or concerns please contact CPFM Design and Construction Owners Rep Jana Gerow at 541-346-8317 or 970-640-0176.