REVISED:
The end date has been changed to Friday, August 18th, at 4:00 pm.
Begin: Wednesday, August 16, 2023, at 2:00 pm
End: Wednesday, August 16, Friday, August 18, 2023, at 4:00 pm
Building(s) or Area(s) Affected: Tykeson Hall
Scope: Due to a faulty steam flow meter and components, the building steam heat will be shut down to install a new meter.
Services Impacted:
- Work will take place in the utility tunnel.
- This work will have little to no impact due to summer weather.
Work Performed By: Hydro-Temp Mechanical
Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.