Begin: Monday, November 25, 2024
End: Friday, January 3, 2025
Building(s) or Area(s) Affected: Lokey Labs plus Huestis Hall room 45
Scope: The lighting control system in Lokey Labs will be repaired. Work will be done from ladders and dust/debris/noise is not expected. They will need access to the listed rooms multiple times throughout December as pieces are demoed, installed, and tested.
Services Impacted:
- Each room will not lose lighting for the entire duration of the project but could expect intermittent loss of lighting as the system is being switched over room by room.
- No loss of power to equipment is expected.
- Contractor will be accessing the following spaces multiple times over the course of the project:
- Lokey Labs 50, 52, 53A, 53B, 53C, 53D, 54, 55, 63, 63A, 64, 66, 70, 72, 74, H73, 83C, 83D, 87A,
- Huestis 45
Work Performed By: EC Electric
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880
Current construction and impacts information can be found on the UO Maps site.