6/27/24 – 6/28/24 Huestis Hall North Office Suites Heating Shutdown

Begin:  Thursday, June 27, 2024, at 6:00 am

End:      Friday, June 28, 2024, at 12:00 noon

Building(s) or Area(s) Affected:  Huestis Hall rooms 200A, 200B, 224A, 224B, 300A, 300B, 321A, 321B

Scope:  To address temperature heating issues in the north office suites, Siemens will install controller devices above the ceilings.

Services Impacted:  Heat will be offline during this time.

Special Instructions:  Occupants are requested to vacate offices during the following times:

6/27 6:00 am – 9:00 am: 200A and 200B
6/27 9:00 am – 12:00 noon: 224A and 224B

6/28 6:00 am – 9:00 am: 300A and 300B
6/28 9:00 am – 12:00 noon: 321A and 321B

Work Performed By:  Siemens

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Huestis Hall rooms 200A-B, 224A-B, 300A-B, 321A-B