Begin: Thursday, August 24, 2023
End: Friday, September 29, 2023
Building(s) or Area(s) Affected: McArthur Court
Scope: Due to the installation of new duct work on the mezzanine at McArthur Court, a number of staircases will be closed as scaffolding is placed to install high runs of ductwork.
Services Impacted: This should only affect the incoming Math department, as they start to use the upper spaces, with the exception of one unoccupied office. There will be no staircase that is blocked, that doesn’t have a second means of access/egress.
The proposed stair closure dates are as follows:
NE corner (S06) 8/25-9/1
SW corner (S76) 9/4-9/8
SW corner (S64) 9/11-9/15
NW corner (S92) 9/18-9/27
NW corner (S02) 9/25-9/29
Work Performed By: GBC Construction/ FM Sheetmetal
Contact: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214
Current construction and impacts information can be found on the UO Maps site.