Begin: Thursday, July 20, 2023
End: Friday, August 4, 2023
Building(s) or Area(s) Affected: McArthur Court
Scope: Due to installation of a ventilation system in the mezzanine level, contractors will be cutting a number of holes to route ducting through. This type of work will produce a lot of noise.
Services Impacted: Work will take place in the Mezzanine, but noise will carry throughout the facility.
Work Performed By: GBC Construction
Contact: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214
Current construction and impacts information can be found on the UO Maps site