UPDATE:
The VFD install will not be complete until after 3:00 pm today and the factory start-up on the VFD is now scheduled for 8:00 am tomorrow morning. Therefore, the shutdown will need to remain in place until tomorrow at approximately 11:00 am 6/27/23.
An update will be sent when the work has been finished.
Begin: Monday, June 26, 2023, at 8:00 am
End: Monday, June 26, 2023, at 12:00 noon Tuesday, June 27, 2023, at approximately 11:00 am
Building(s) or Area(s) Affected: Lokey Labs
Scope: Emergency shut down of all fume hoods to complete repairs and replace equipment.
Services Impacted: This will affect exhaust and fume hoods.
Special Instructions: Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.
Work Performed By: EC Electric and Lewis Construction
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880