Begin: Monday, February 27, 2023, at 7:30 am
End: Wednesday, March 1, 2023, at 3:00 pm
Building(s) or Area(s) Affected: HEDCO
Scope: Due to the installation of a new Chilled Water meter, the building air conditioning system will be shutdown.
Services Impacted: Because of winter weather, this outage should have little to no impact on building users.
Work Performed By: S2 Industrial
Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.