UPDATE: We were informed that this was previously restored.
REVISED:
Only one of the building’s two vacuum pump systems is down.
The operation of the fume hoods will not be impacted and are still functional.
Parts are being ordered to repair the system.
Begin: July 22, 2022
End: Unknown
Building(s) or Area(s) Affected: Klamath Hall
Scope: The house vacuum is not functioning. Investigation revealed that new parts are needed and a contractor will be called to perform repairs. Repairs are currently estimated to take one week but an update will be sent when more is known.
Services Impacted: Fume hoods will be impacted by the house vacuum shutdown.
Special Instructions: Fume hood sashes should be closed and containers within the fume hoods sealed.
Work Performed By: A Contractor
Contact: Kyle Harshbarger, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406