5/12/22 – 5/25/22 ZIRC Chilled Water, Treated Steam, and Untreated Steam Shutdown

UPDATE 5/20: Additional shutdowns will be required. Times and dates are still being reviewed by all that will be involved. Activities will be completed next week on Monday 5/23 and/or Wednesday 5/25. The project team will communicate with building users once times are confirmed.

Begin:  May 12, 2022 at 06:00 am

End:      May 19, 2022 May 25, 2022 at 05:00 pm

Building(s) or Area(s) Impacted:  Zebrafish International Resource Center

Scope:  Utility meter installation will require that we shut down the chilled water, treated steam, and untreated steam to the building.

Services Impacted:

  • The chilled water and treated steam will be restored same day on the 12th.
  • The untreated steam to the building will be off until May 19th to allow time to complete work associated with that system.

Work Performed By:  Fortis Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972