ZIRC Annex Demolition Advisory 11/16/20 – 11/25/20

DATE REVISION:

The date for this project is from 11/16/20 through 11/25/20.

 

Begin:  Monday, November 16th, 2020 at 6:00 am

End:      Wednesday, November 18th 25th, 2020 at 5:00 pm

Building(s) or Area(s) Impacted:  ZIRC Annex

Scope:  Asbestos abatement and demolition of building.

Services Impacted:  Construction related noises and activities can be expected.

Work Performed By:  ATEZ

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972