Knight Library Chilled Water Supply Pipe Shutdown 11/12/20 and 11/13/20

UPDATE 11/12/20:

During the Knight Library chilled water meter replacement, an adjacent pipe fitting was found to be leaking. A brief shutdown Friday, November 13th, 8:00am to 12:00pm is required to repair the pipe fitting.  This should have very little impact on building users.

Begin:  Thursday, November 12th, 2020 at 7:00 am

End:      Thursday, November 12th, 2020 at 4:00 pm

Building(s) or Area(s) Impacted:  Knight Library

Scope:  Due to a failed utility meter, the north chilled water pipe supplying Knight Library will be shutdown to install a new meter.

Services Impacted:  The shutdown to the chilled water should have minimal impact to building users.

It is important to note that this shutdown will not affect the chilled water to the Special Collections section of Knight Library, which is supplied via piping on the south side of the building. 

Work Performed By:  UO CPFM – Utilities & Energy Pipe Fitters

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246