Begin: Thursday, October 15th, 2020 at 7:00 am
End: Thursday, October 15th, 2020 at 3:00 pm
Building(s) or Area(s) Impacted: Human Physiology Tenant Improvement at Practice Level of the northwest corner of Hayward Field (building grid lines 75 to 89)
Scope: The Hayward Field fire sprinkler system in Zone 4 will be shut down to relocate an existing main sprinkler line that interferes with TI construction at grid line 85.
Services Impacted: Only Zone 4 will be in fire alarm test mode.
Extra Notes: IES will provide fire alarm assistance. Fire watch will be a joint effort between Harvey & Price and GBC Construction.
Work Performed By: Harvey & Price
Contact: Gene Mowery, CPFM Owner’s Representative, 541-346-5593