LISB First Floor Fire Testing 8/18

Begin:  Tuesday, August 18, 2020 at 7:00 am

End:      Tuesday, August 18, 2020 at 8:00 am

Building(s) or Area(s) Impacted: Lewis Integrated Science Building 1st Floor

Scope: Contractors will be testing the new fire alarm and strobe system as part of the LCNI MRI renovation project.

Extra Notes: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time.  Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures. If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations. Please contact Zach Earl, Fire Systems Program Manager, 541-346-9295 (Office) or 541-521-0351 (Mobile) with questions.

Work Performed By: GBC Construction

Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880