Begin: Friday, February 28th, 2020 at 6:30 am
End: Wednesday, March 4th, 2020 at 5:00 pm
Building and Areas Impacted: Thompson University Center’s Break Room 308, Mechanical Room 309, 3rd Floor Hall, and South Stairwell
Scope: Install mini split unit in room 308
Services Impacted:
- The south stairwell and room 308 may not be available for use during Friday, 2/28/2020, through Wednesday, 3/4/2020.
- There will be noise on the roof, south stairwell, 3rd floor halls and room 308 throughout the project.
Proposed Schedule:
- Friday, 2/28/2020, 6:30 am – a crane will be onsite to lift equipment to the south roof.
- Monday and Tuesday, 3/2 to 3/3/2020, Alliant Systems will have an electrician and service technician onsite to install the indoor and outdoor units.
- Wednesday, 3/4/2020, project is scheduled to be completed by end of day.
Extra Notes: Work will be performed by Alliant Systems
Contact: Melinda Seeley, CPFM Real Estate Prop Specialist, 541-346-5550