Allen Hall 2nd Floor Fire Sprinkler Shutdown 12/20/19

Begin:  Friday, December 20th, 2019 at 6:00 am

End:      Friday, December 20th, 2019 at 12:00 noon

Building Impacted:  Allen Hall

Scope:  2nd Floor fire sprinkler system will need to be shut down to move a sprinkler head associated with the installation of a new fan coil unit.  This is an unexpected shutdown due to adjustments in design.  Work to take place at office suite 216.

Services Impacted:  2nd Floor Fire Sprinkler System will be offline.  The building will be monitored during this time.

 ContactGene Mowery, Owner’s Representative, 541-346-5593