Campus Community,
As part of ongoing utility service work for the Black Cultural Center project, the fence line will be changing on the west and north ends of the project site.
The fence line on Villard Alley has been shifted to accommodate construction vehicle access points.
The sidewalk on 15th in front of the project will be closed starting Monday 3/25 and reopened on Thursday, 3/28 to allow for a new domestic water vault to be excavated and installed at the NE corner of the site. Pedestrian traffic will be routed to the north side of E 15th Ave.
For questions or concerns please contact CPFM Design and Construction Owners Rep Martina Oxoby at 541-346-5880.