As part of the Tykeson Hall construction project, Fortis Construction will be repaving the sidewalk and ADA ramp from 13th Ave to the west entrance of Johnson Hall. ADA access will NOT be available during Spring Break, from March 23 – March 31. For ADA access to Johnson Hall, please call VPFA Office Staff at 541-346-3003. Additional site work will also be completed during this time. All thru-way pedestrian and bike traffic will be rerouted to the east side of Johnson Hall.
Sequence of work:
Saturday 3/23
Relocate site fence to incorporate sidewalks on north and east
Start Demo
Monday 3/25 – Friday 3/29
Demo sidewalks
Excavate for walks and Johnson rain drain
Install drain connections, backfill
Prep, form and pour sidewalks
Strip forms, tune up grading at walks
Saturday 3/30 – Sunday 3/31
Return fence to the original location on the east site boundary
Fence on 13th to remain in place, incorporating 13th sidewalk thru 5/31/19
General Project Questions: Martina Oxboy 541-346-5880
ADA Access: VPA Office Staff 541-346-3003