UO Klamath Hall 3rd Floor Laboratory Renovation Construction Logistics and Construction Notice

Campus Community,

Beginning on December 10th contractors will start mobilizing for construction to renovate the 3rd floor of Klamath Hall. Provided here is the construction logistics plan showing staging in and around the Streisinger Hall loading dock and construction office trailers in the lawn southwest of Streisinger Hall. A couple of key things to note.

1. No staff, faculty or visitor parking will be impacted. Two service vehicle locations at the Streisinger loading dock will be out of service. For a short duration of two months in the summer of 2019, two ADA stalls will be out of service. More details will follow as the summer approaches.

2. The Streisinger loading dock and the west truck bay of the dock will remain accessible for campus use throughout the project. The Streisinger dock and elevator will not be used by or for construction.

3. Construction access to the 3rd floor and rooftop of Klamath will be accessed via a temporary construction hoist/elevator located within construction fencing in the east bay of the Streisinger loading dock. Access will be up and over.

4. Existing exterior pedestrian and bike paths will remain open.

Schedule:

The current construction schedule is December 2018 through September 2020. This December 10th through January 4th contractors will be installing construction fencing, construction office trailers, scaffolding, and the temporary construction hoist/elevator as shown in the provided logistics information within this notice.

A Neighborhood meeting will be held this Wednesday, November 28th at 12 pm in the Visualization Lab of the Price Science Commons & Research Library, Room B006. Please come to hear project information, further construction details and to pose any questions or concerns you have.

For questions or concerns please contact CPFM Design and Construction Project Manager Denise Stewart at 541-335-1258 or emailĀ dstewart@uoregon.eduĀ 

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/11/Klamath-3rd-Construction-Logistics_Campus-Notice_11-20-2018-1-qxavhj.pdf” download=”all” viewer=”google” ]