6/5 – 6/8: [PACIFIC HALL] Air Balancing Contractor Access Advisory

Building Occupants,

 

As part of the ongoing Pacific B-2 Renovation, contractor Air Inc. will be starting to balance the north wing HVAC system. This will be a process over the summer as we finalize spaces and verify space requirements. This work will not disrupt building systems but will require 2-3 people going into each area to verify HVAC grilles and balance those systems. Some ladder work will be necessary.

 

Phase 1 Schedule

Area: Date:
North Wing Basement Tuesday, 6/5
North Wing 1st Floor Wednesday, 6/6
North Wing 2nd Floor Thursday, 6/7
North Wing 3rd Floor Friday, 6/8

For questions or concerns, please contact CPFM Design and Construction Project Manager Nick Pritchard  541-346-9139.

 Future phases will be scheduled in the coming weeks and updates will be provided.

PAC Testing & Balancing (1)-2bc16pd

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/06/PAC-Testing-Balancing-1-2bc16px.pdf” download=”all” viewer=”google” ]