From December 11 – 22, 2017 Delta Construction will be onsite completing three sidewalk repairs/replacements. There will be noise, congestion and pedestrian closures associated with this work.
13th Avenue – Ford Alumni to Hamilton Sidewalk Repair
Date | Scope |
12/11 | Setup Traffic Control, Saw Cutting, Erosion Control, start removal of sidewalk. |
12/12 | Continue sidewalk removal and prep for sidewalks. |
12/13 | Complete removal and prep, start forming for sidewalks (cover subgrade with blankets if temperature requires). |
12/14 | Complete forming and pour sidewalks. |
12/15 | Strip forms, backfill with loam, and clean up. Open sidewalks if they are not to green. |
12/18 | Pick up remaining traffic control, final clean up. |
13th Avenue – Chapman Hall Sidewalk Replacement
Date | Scope |
12/11 | Setup Traffic Control, Erosion Control, and Saw Cutting. |
12/13 | Setup Traffic Control, Erosion Control, and Saw Cutting. |
12/14 | Form and pour back curb and sidewalk. |
12/15 | Strip, back fill, remove traffic control, and clean up. |
15th and Agate – NW Corner Sidewalk Replacement
Date | Scope |
12/18 | Setup Traffic Control, Erosion Control, Saw Cutting, start removal of sidewalk. |
12/19 | Complete sidewalk removal and prep for new sidewalks. |
12/20 | Form new sidewalks, possible placement of sidewalks. |
12/21 | Pour sidewalks. |
12/22 | Strip sidewalks, backfill w/loam, clean up, and remove traffic control. |