12/11 – 12/22: [13TH Ave & 15TH Ave] Sidewalk Repairs & Replacements

Campus Community,

From December 11 – 22, 2017 Delta Construction will be onsite completing three sidewalk repairs/replacements. There will be noise, congestion and pedestrian closures associated with this work.

 

                                                                            13th Avenue – Ford Alumni to Hamilton Sidewalk Repair

 

Date Scope
12/11 Setup Traffic Control, Saw Cutting, Erosion Control, start removal of sidewalk.
12/12 Continue sidewalk removal and prep for sidewalks.
12/13 Complete removal and prep, start forming for sidewalks (cover subgrade with blankets if temperature requires).
12/14 Complete forming and pour sidewalks.
12/15 Strip forms, backfill with loam, and clean up. Open sidewalks if they are not to green.
12/18 Pick up remaining traffic control, final clean up.

 

                                                                                 13th Avenue – Chapman Hall Sidewalk Replacement

 

Date Scope
12/11 Setup Traffic Control, Erosion Control, and Saw Cutting.
12/13 Setup Traffic Control, Erosion Control, and Saw Cutting.
12/14 Form and pour back curb and sidewalk.
12/15 Strip, back fill, remove traffic control, and clean up.

 

                                                                               15th and Agate – NW Corner Sidewalk Replacement

 

Date Scope
12/18 Setup Traffic Control, Erosion Control, Saw Cutting, start removal of sidewalk.
12/19 Complete sidewalk removal and prep for new sidewalks.
12/20 Form new sidewalks, possible placement of sidewalks.
12/21 Pour sidewalks.
12/22 Strip sidewalks, backfill w/loam, clean up, and remove traffic control.

 For questions or concerns regarding this notification, please contact CPFM Zone D and Exterior Manager Kevin Farthing at 541-346-2857.