03/27/17-03/29/17: Continued work associated with the SCUA HVAC Project at The Knight Library.

Campus Community,

As part of continued work associated with the SCUA HVAC Project at The Knight Library.  Below are details about the Crane Pick located at the southeast corner taking place Monday, March 27 – Wednesday, March 29, 2017.
Monday, March 27
7:00 am – 4:30 pm
Contractors set up barricades and trench plates.
Tuesday, March 28
7:30 am – 4:30 pm
The arrival of the crane, set up, and the crane picks mechanical equipment off the rooftop.
Wednesday, March 29
7:30 am – 4:30 pm
Contractors remove barricades and trench plates.
Access Affected:
On the southeast corner of the main library, the driveway will be partially blocked, and the walk area between Knight Library and Gerlinger Annex will have a large crane set up.  Additional delivery equipment will be in the area.

For questions regarding this notification contact Jana Gerow, Campus Planning and Facilities Management, Design and Construction at 541-346-2017