Begin: Wednesday, October 26th, 2022 at 7:00 am
End: Wednesday, October 26th, 2022 at 12:00 pm
Building and Area: Huestis Basement
Scope:
- The basement supply and exhaust air will be shutdown to allow for an exterior snorkel attachment on the outside air intake.
- Willamette AHU-2 and Huestis SF3B and AHU 1 & 2 will be offline during this time
Services Impacted: Exhaust and HVAC Air Supply
Work Performed By: JH Kelly, FM Sheetmetal, and Siemens
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880
To view current construction and impacts. visit UO Map.