Begin: Monday, March 1st, 2021
End: Friday, March 19th, 2021
Building(s) or Area(s) Impacted: Lillis Hall – hallway H260
Scope: Facilities Services will be removing the existing water fountain on the 2nd floor east hallway and replacing it with a new fountain that includes a bottle filler.
Services Impacted:
- The drinking fountain in H260 will be offline until the new fountain is installed
- Users can expect to see Facilities Services personnel, including plumbers, carpenters, electricians and painters working in the area intermittently for the duration of the project.
- Users can expect to hear normal and occasional construction noises such as hammering and drilling, and may smell a water-based latex, non-toxic paint, during the process.
Extra Notes: No other utility disruptions or shutoffs are expected at this time, however, if there are any more, an additional notice will be distributed.
Work Performed By: UO CPFM Facilities Services Crews
Contact: Justin Grishkin, CPFM Construction Services Manager, 541-346-5242