Lillis Hall Drinking Fountain Advisory 3/1/21 – 3/19/21

Begin: Monday, March 1st, 2021

End: Friday, March 19th, 2021

Building(s) or Area(s) Impacted: Lillis Hall – hallway H260

Scope: Facilities Services will be removing the existing water fountain on the 2nd floor east hallway and replacing it with a new fountain that includes a bottle filler.

Services Impacted:

  • The drinking fountain in H260 will be offline until the new fountain is installed
  • Users can expect to see Facilities Services personnel, including plumbers, carpenters, electricians and painters working in the area intermittently for the duration of the project.
  • Users can expect to hear normal and occasional construction noises such as hammering and drilling, and may smell a water-based latex, non-toxic paint, during the process.

Extra Notes: No other utility disruptions or shutoffs are expected at this time, however, if there are any more, an additional notice will be distributed.

Work Performed By: UO CPFM Facilities Services Crews

Contact: Justin Grishkin, CPFM Construction Services Manager, 541-346-5242