Begin: Wednesday, August 12th, 2020 – Currently
End: unknown
Building or Area Impacted: University Health, Counseling, and Testing Center
Scope: Heating in the Health Center is currently being impacted due to equipment damage from a pipe leak. Parts have been ordered to fully replace the damaged equipment and LCL is working on installing temporary equipment to mitigate any impacts.
Services Impacted:
- Building heat impacts may be observed for 1-2 weeks.
- This will not impact air changes and running 100% outside air through the building while it is occupied.
Work Performed By: Lease Crutcher Lewis
Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972