Campus Community,
Below is a list of closure dates related to the Hayward Field Cell Tower Project.
Schedule of Closures
Affected Areas: Hayward Field, Recreation Fields 3 & 4 and Hayward Field access road off of 18th Ave.
Date: 1/23/17
A large crane with 180-foot boom will arrive on site and be set up. This crane will be on site until 1/25/17.
A second crane or lift will also arrive on 1/23/17 and remain on site for approximately 4 weeks and will remain in the fenced construction area.
Date: 1/24/17 – 1/25/17
Time: 7 am – 7 pm
The vehicle, bike, and pedestrian traffic, will be restricted from where vehicles turn off of 18th to the north to access the Hayward Cell tower construction site, including a 90-foot radius around the tower as shown in the attached drawing.
Trucks with portions of the cell tower will arrive and be constructed on the foundation immediately adjacent to the cell tower building which is under construction between the hammer throw area and recreation field #3. Following the raising of the tower, the crane will be disassembled and removed from the site.
Date: 2/6/17 – 2/7/17
Time: 7 am – 7pm
Trucks with the remaining cell tower portions will arrive and be constructed.
A third large crane will arrive and remain onsite until 2/7/17.
To ensure the safety of the campus community traffic control barriers, signage, and flaggers will be in place. Please avoid this area during the above-listed dates.
For questions about this project, please contact Jana Gerow at 541-346-6837.