Begin: Friday, June 28, 2024, at 7:00 am
End: Friday, June 28, 2024, at 3:00 pm
Building(s) or Area(s) Affected: Huestis Hall
Scope: The lab vacuum pump system will be shut down to install a new fabricated muffler section to reduce noise and vibration transference through the vacuum duct work on levels 1, 2 and 3.
Services Impacted: End users in Huestis Hall will not have lab vacuum service available at the turrets at lab benches and in fume hoods.
Special Instructions: Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.
Work Performed By: FM Sheetmetal
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880
Current construction and impacts information can be found on the UO Maps site.