2/10/25 – 2/13/25 Klamath Hall, Willamette Hall, Lokey Labs, Lewis Integrative Science Building Process Chilled Water Work Advisory

Begin:  Monday, February 10, 2025

End:      Thursday, February 13, 2025

Building(s) or Area(s) Affected:  Klamath Hall basement and 1st floor / Willamette basement, 1st , 2nd, and 3rd floors / LISB basement, 2nd, and 3rd floors / Lokey Labs.  (Please see attached maps for specific locations affected.)

Scope:  Process chilled water system could see minor fluctuations in pressure and flow while a water balancing contractor makes final adjustments to the system.

Services Impacted:  Balancer will be required to enter labs that have PCW drops to take readings and make adjustments.

Work Performed By:  Air, Inc.

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315 or 541-525-4326

Current construction and impacts information can be found on the UO Maps site.

LISB Map

Lokey Labs

Willamette

Klamath