UPDATE:
The dates and times have been revised from 7/25 and 7/26 to the schedule below:
- 1st Day: Thursday, August 1, 2024, from 6:00 am to 7:00 am
- 2nd Day: Friday, August 2, 2024, from 6:00 am to 7:00 am
Begin: Thursday, July 25, 2024, at 6:00 am
End: Thursday, July 25, 2024, at 8:00 am
1st Day: Thursday, August 1, 2024, from 6:00 am to 7:00 am
2nd Day: Friday, August 2, 2024, from 6:00 am to 7:00 am
Building(s) or Area(s) Affected: Klamath Hall Third Floor
Scope: Fire alarm and suppression system will be shut down for the third floor of Klamath Hall to complete sprinkler line adjustments on the roof. Contractor will provide fire watch.
Details: Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.
Special Instructions: If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations
Work Performed By: Harvey & Price
Contact: Waymon Banks, CPFM Owner’s Representative, 541-346-0196